How long does a full riad renovation take?
Twelve to twenty-four months for a medina riad done properly. Longer if you're replacing zellige, tadelakt, or cedar work at scale.
A full restoration of a medina riad — structural, plumbing, electrical, finishes, and craft work — typically takes twelve to twenty-four months in Marrakech when done to a traditional standard. Faster timelines exist but usually compromise on the craft work; longer timelines are common when the building throws up structural surprises or when the craft specification is ambitious.
The phases run roughly as follows. Structural and building permit work — demolition of any unsalvageable elements, structural repairs, updating foundations where needed, and securing the permis d'habiter process — typically takes three to four months on a well-planned project. Systems work — plumbing, electrical, drainage, water supply — runs four to six months and overlaps with the structural phase. Surface and finish work — tadelakt, zellige, bejmat flooring, cedar ceilings, gebs plaster, painting — runs six to ten months depending on scope and the number of maalems working simultaneously. Furnishing and commissioning adds another month or two.
Craft work is usually the critical path. A good tadelakt maalem applies the plaster over weeks, not days, and the work cannot be rushed — the lime needs time to cure. A zellige installation for a full riad's courtyard, fountain, and wall details can take two to three months with a team of three maalems working steadily. Gebs and zouak add further time. The buildings that restore fastest are the ones with smaller craft scopes; the buildings that take longest are the ones that restore original elements to a proper standard.
Foreign owners managing renovation remotely should expect delays beyond the plan. Monthly visits or a reliable on-ground project manager are essential. A renovation that runs 30% over the original timeline is not a failure; it's typical. A renovation that doubles the timeline is a sign of a mismanaged project, and the causes usually have names — a contractor stretched too thin, an architect who lost engagement, an owner who kept changing the specification.
Tadelakt, Zellige, Bejmat, Gebs, Zouak, Maalem, Permis d'habiter